|
|
The Contract Disputes Act establishes an administrative law process for pursuing and resolving claims and disputes involving Government contracts. The attorneys of Petrillo & Powell have lengthy and broad experience in all aspects of this process, including the preparation of contract claims and appealing Contracting Officers final decisions. We have prepared and negotiated requests for equitable adjustment arising out of change orders, constructive changes, terminations for convenience, and other compensable events. We have defended contractors from Government claims and counterclaims, and terminations for default. Claims We regularly assist clients in preparing, submitting, and negotiating claims for equitable adjustment, and for other relief, both monetary and non-monetary. Some examples include:
Terminations for Default When the Government threatens to terminate the contract for default, we assist our clients in presenting cogent and timely arguments opposing termination. When a default termination does occur, we assist in opposing it and limiting the collateral consequences.
Litigating Disputes Most claims are resolved through settlement, but when that isnt feasible, we pursue a contractors rights in a formal legal proceeding, or through alternative dispute resolution. The attorneys of Petrillo & Powell, P.L.L.C. have litigated a wide variety of Government contract disputes before the Boards of Contract Appeals, the Court of Federal Claims, and the Court of Appeals for the Federal Circuit. Recently, the firm has handled the following appeals at the Boards of Contract Appeals: 1. Community Consulting International, ASBCA No. 53489, Aug. 2, 2002.
2. Sentara Health System, Inc., ASBCA No. 51540, 99-1 BCA ¶ 30,323, and ASBCA No. 51540, 99-2 BCA ¶ 30,454 (1999). These related decisions involved Sentara Health Systems claim for the contractors share of value engineering savings realized by the Department of the Navy as a result of adopting Sentaras value engineering change proposal. The VECP had suggested a new method for fulfilling certain data collection activities at the health care clinics operated by Sentara for CHAMPUS beneficiaries. The Navy moved to dismiss the Appeal for failure to state a claim because at the time Sentara submitted its VECP, the contract had not yet been modified to add the requirement which was the subject of the VECP. After briefing, the Board denied the motion to dismiss. The Navy moved for reconsideration of this decision, which was also denied. Following a three day hearing, the Board held for Sentara on the issue of entitlement. Sentara Health Systems v. Department of the Navy, 2001-1 BCA ¶ 31,198 (2000). The Navy appealed this decision to the Court of Appeals for the Federal Circuit. Subsequently, the parties agreed to settle the case and the Government withdrew its appeal. 3. T&M Distributors, Inc., ASBCA No. 51405, 1999 WL 1116977 (1999). T&M had filed a claim for constructive changes to its indefinite delivery, indefinite quantity contract with the Defense Logistics Agency. After trial, the judge decided the issue of entitlement in T&M’s favor. The Board found that the parties’ course of dealing over the life of the contract had established an implied term which was binding on the Government concerning the manner and rate of Defense Logistics Agency ordering under the contract. The Board found that the agency had acted contrary to this implied term which had, as a result, increased the contractor’s costs for performing the contract and that the contractor was therefore entitled to compensation under the contract’s changes clause. 4. A Government agency assessed credits against our client for late performance of services. We appealed from the contracting officers final decision to the U.S. Court of Federal Claims. After discovery, we were able to negotiate a favorable settlement of the matter.
Other matters in which members of the firm have participated include the following reported and unreported matters. 1. T&M Distributors, Inc. v. United States, 1998 WL 118077 (Fed.Cl.), affd 185 F.3d 1279 (C.A.F.C. 1999) (whether the terrmination of a contract for convenience was proper, or was a breach of contract, when it resulted from the contractors notification to the Government that the information in the solicitation was inaccurate). 2. International Transducer Corp., v. U.S., 30 Fed. Cl. 522 (1994) (contractor brought claim based on constructive change theory for increased unit costs). 3. Container Systems Corporation, Inc., ASBCA No. 40,611, 94-1 BCA 26,354 (1993) (contractor appeal of termination for default). 4. Standard Technology, Inc., ASBCA No. 41831, 91-2 BCA 23936 (1991) (Board denied Government motion to dismiss claim on procedural and jurisdictional grounds). 5. Detyens Shipyards, Inc., GSBCA No. 10707-COM and 10449-COM, 1990 WL 191,743 (1990) (notice of settlement and dismissal of claim involving contractors request for equitable adjustment and Government counterclaim for defective workmanship). 6. Tektronix, Inc., v. U.S., 216 Ct. Cl. 144 (1978) (Case involving computation of damages for patent infringement by Government contractors). 7. Negotiation of settlement in lieu of debarment. 8. Negotiation of guilty plea/consent judgment to minimize risk of debarment or suspension. 9. Negotiation of settlement of claims for increased costs resulting from inadequate Government-owned, contractor-operated production facilities (several separate contracts for multiple clients). |
Home - Our Attorneys - Public Contract Sites - Your Comments